Having a construction plan drawn up: It's all in the details.
Having the construction plan drawn up is often the first step on the way to realizing a real estate project: for good reason, because it is the construction plan that will later be submitted to the responsible building authority—and for obvious reasons, the authority will not be satisfied with simple sketches or floor plans. Anyone who wants to draw a construction plan or have one drawn must be sure of the greatest possible precision and also strictly adhere to the standards specified by law.


What exactly does drawing a construction plan entail?

Drawing up a construction plan is more complex than creating a floor plan.

When professionals draw up a construction plan, it serves important purposes:
- It is used as part of the approval process by the building authorities, who naturally ensure that the project is implemented correctly.
- It promotes smooth coordination between all parties involved in the project, as they are working with the construction plan on a uniform and standard-compliant basis.
- A detailed construction plan prevents misunderstandings, helps to avoid delays, and thus generally serves to prevent errors—which in turn reduces the risk of avoidable follow-up costs.
- Having a professional construction plan drawn up can also facilitate project implementation by avoiding delays due to unclear specifications.

What standards must be taken into account when having a construction plan drawn up?
- State building regulations, which may vary from state to state
- DIN standards such as 1356-1, which defines the principles for construction drawings
- DIN 277 for area and room calculation
- DIN 4102, which contains important fire safety requirements
- DIN 18065, which includes requirements for stairs and dimensions, among other things
A scale of 1:100 is common when having a construction plan drawn up. For individual building details that require enlargement, a different scale is usually used, e.g., 1:50 or 1:20. In addition, requirements from the Building Energy Act (GEG), which replaced the previously applicable Energy Saving Ordinance (EnEV), must be taken into account. When having the construction plan drawn up, these requirements concern, for example, energy efficiency, wall thickness, and insulation.

The construction plan as a complete work
All information has been compiled to the best of our knowledge. However, we cannot accept liability for the details.